Dune Palms Road is now open in both directions.
CURRENT UPDATE
Current Update | Actualizacion Actual
Dune Palms Bridge Project Update:
Week of May 20
Photo
Crews continue working on the temporary bridge support system.
Foto
Las cuadrillas continúan trabajando en el sistema de soporte temporal del puente.
PROJECT TIMELINE
PROJECT PROGRESS
Dune Palms Project Timeline
The Northbound Bridge is NOW OPEN in BOTH directions.
Here are the next steps, with an estimated completion date in Spring 2025.
Linea del tiempo de el proyecto Dune Palms
El puente en dirección norte está ABIERTO en AMBAS direcciones
Estos son los próximos pasos, con fecha estimada de finalización en 2025.
INSTAGRAM POSTS
BRIDGE & PROJECT DETAILS
The newly constructed 480-foot-long bridge will be approximately 86 feet wide and feature:
- 4 vehicle travel lanes, 2 in each direction
- 2, 8-foot-wide bike/cart paths, 1 in each direction
- 2, 6-foot-wide sidewalks, 1 in each direction
- A 9-foot, 8-inch raised center median
The project also will complete bridge approach roadway improvements (including drainage) to accommodate the raised profile for the bridge, and it will tie into the CV LINK multi-use trail under the bridge and at two secondary connecter trails from Dune Palms Road.